Building contract claims.
Many building projects are the subject of claims - the assertion of a right, usually by the contractor, to an extension of the contract period or an additional payment under the terms of the building contract. Many of these claims are unsound or ill-founded, often because the basic principles are mi...
Κύριος συγγραφέας: | |
---|---|
Συγγραφή απο Οργανισμό/Αρχή: | |
Μορφή: | Ηλ. βιβλίο |
Γλώσσα: | English |
Έκδοση: |
Oxford :
Wiley-Blackwell,
2011.
|
Έκδοση: | 5th ed. / |
Θέματα: | |
Διαθέσιμο Online: | Full Text via HEAL-Link |
Πίνακας περιεχομένων:
- Front Matter
- Part I. Introduction
- Time
- Liquidated Damages
- Basis for Common Law Claims
- Direct Loss and/or Expense
- Points of Principle
- Potential Heads of Claim
- Causation
- Global Claims
- Preparation and Substantiation of Claims
- Part II. Extension of Time under JCT Standard form Contracts
- Liquidated Damages under JCT Standard form Contracts
- Loss and/or Expense under JCT Standard form Contracts
- Variations
- Part III. Claims Under the General Conditions of Government Contracts for Building and Civil Engineering Works (GC/Works/1(1998))
- Claims under the ACA Form of Building Agreement (ACA 3)
- Claims under the ACA Standard Form of Contract for Project Partnering (PPC2000)
- Claims under NEC 3 Engineering and Construction Contract (NEC 3)
- Sub-Contract Claims
- Appendix. Example of Contractor's Claim for Reimbursement of Direct Loss and/or Expense Under SBC with Quantities clauses 4.23₆4.26 ₆ Architect's and Quantity Surveyor's Assessment with Commentary
- Table of Cases
- Table of Standard form Contract Clauses
- Index.
- Introduction
- Time
- Liquidated damages
- Basis for common law claims
- Direct loss and/or expense
- Points of principle
- Potential heads of claim
- Causation
- Global claims
- Preparation and substantiation of claims
- Extension of time under JCT standard form contracts
- Liquidated damages under JCT standard form contracts
- Loss and/or expense under JCT standard form contracts
- Variations
- Claims under GC/Works/1
- Claims under ACA 3
- Claims under PPC2000
- Claims under NEC 3
- Sub-contract claims.